Towcester A43 Roundabout Works - Update, 20th December 2024

Posted in Roads & Transport

Update from Zac Hurst, MD, Persimmon Homes Midlands:

Phase 1 of the programme commenced in November and vegetation clearance has been completed. Temporary crossovers in the central reservation have also been installed.

Details for Phase 2 and 3 are as follows:

Phase 2: 6th January to 14 May 2025
A43 Southbound closed with the Northbound carriageway operating as a contraflow

Phase 3: End o May to mid-June 2025
A43 Southbound and Northbound lane 2 closure

The A43 will be fully open again in time for the MotoGP which we recognise is an important event in the Silverstone calendar.

A 24/7 emergency recovery service for vehicle breakdowns within the working area will be provided throughout the period of these works.

We understand that construction activities can be disruptive, and we are committed to minimising the impact on local businesses and residents. During the construction period, there may be temporary road closures and diversions. We will ensure that clear signage is in place to guide traffic and that access to properties is maintained at all times.

Our contractors will continue to provide regular updates on the progress of works through their website and social media channels. For any queries, please contact Jackson Civil Engineering Public Liaison Officer, Yazmin Parry at yazminparry@ryrltd.com

We are committed to keeping local residents and businesses informed of progress and will provide regular updates as well as our dedicated website www.resident-portal.co.uk/towcester which has been developed so the latest information regarding these works can be viewed at any time.

We appreciate your patience and cooperation during this period and regret any inconvenience caused. These improvements are essential for the long-term benefit of the community, and we are committed to completing the works as efficiently and safely as possible.